Project Workload for Information
last Updated 23 May 2025 [updated weekly]
Please note that workload is dealt with in the order that it was appointed. As we also work with Local Authorities, Building Control, Other Consultants, Manufacturers, Suppliers, Clients, Builders, Contractors there is a lot of tooing and froeing and downtime on a project. - - - - - - -
- Where planners consult us on live applications, they will usually set a short often 7 day deadline for responses to consultations to be provided. They will then request a 30 day period for them to respond, but this is often exceeded. We need to deal with planning responses, and slot these in, in between existing workload, as and when they arise.
- Where projects are on site we will need to slot in Site Inspections into our workload to suit the progress of works on site
- Where projects are on site we will need to respond to site queries to suit site progress, any materials or manufacturing supply issues, and Contractors queries, slotting these into our workload.
- We will need to respond to Manufacturers queries/comments / Tender procedures to suit project pre construction progress and slot these into our workload
- We will need to respond to Building Control queries/comments to suit pre construction sign off and site progress and slot these into our workload
- Where we are CA or PM on any project on site, we need to slot CA and PM management into our workload to suit progress of work on site
- CPD - As Architects we are and have always been required to carry out 37 hours CPD to ensure we are up to date on a range of topics, we have previosuly only had to record hours on range of subjects internally - for 35 years. .
Since 2024 we now need to record this formally on ARB and RIBA database confirming how each activity has benefitted are continuing proffessional development.
- Principal Designers Registration process
Following changes to the Principal Designers role and Regulation processes we are now required to formally take a competance test and register on the RIBA register of Principal Designers before the end of December 2025. The initial process for this has required a 6 week Fire Safety course, and a 6 week Principal Designers course to run through all of the changes in how Principal Designers services are to be provided and how the Building Control applicaiton process and the information required is now operated. The process also involves preparing a CV of proects showing past experince.
We are living in a completely different 'world' . [despite haveing carried out the PD role for 35+ years]
Building Control Officers went through a similar process last year , beware Contractors and Builders are next in the registration and proving competance process.
Current Active Workload
Stage 1: Survey and Existing model prep: - 23-044, 25-011,
Stage 2 & 3 Design:- 23-060, 24-055 (Ph2), 24-055 (Ph3), 24-079,
Stage 3C Consultation:- 22-035, 23-053, 24-037, 24-055 (Ph1), 24-055 (Signage), 25-008
Stage 3D Discharge:- 22-014,
Stage 4A: Technical Design: -
Stage 4B: Technical Design: -13-062 [B2] from Eaves
Stage 4C: Technical Import SE, M&E, Other Consultant liaision 22-058, 23-060, 24-055
Stage 4T: Tender and BCO Plan Check: - 13-062 [B2], 22-058, 24-047
Stage 5: On Site: - 13-062 [B2], 22-014, 24-055 (Ph1)
Stage 5: On Site with PC Advisory only: - 24-004
Stage 6: Completion:- 13-062 [B1], 20-019, 20-054, 23-006,
Quotes: see below
Projects
13-062 - The Prize Buildings Block One- 3no 2S2B Residential Retirement Cottages
Appointment: Architect, PD, Cert
Unit One - Certified Complete and occupied
Unit Two - Painting, commissioning, certification
Unit Three - Certified Complete and occupied
13-062 - The Prize Buildings Block Two- 4no 2S2B Residential Retirement Cottages
Appointment: Architect, PD, Cert, PM Advisory
- Foundations complete Jan 2023, Inspected
- Substructures on site, Inspected to 13 May Beam and block imminent
- F10 notification required
- BCO Applicaiton submitted Plan check in progress.
- BCO next Site inspection Top of Beam and block
- Architect next Site inspection as Beams being Installed and then Top of Beams underslab drains complete
- Beam and Block - order finalised 22 May 2025
- Walling to US Wallplate - Design complete, rechecked, Prints and explanatory emails to be issued 23 May 2025 .
Materials being sourced, Floor blocks - done, walling quantiies to be allocated
Insulation in progress, bricks in progress,
In current workload .
- GF Lintols and Beams - Architects complete - Issued for pricing
- Windows and External Doors - Tender in Progress
- Rooflights Set Out - Issued for Pricing
- Vetical Levels - finalised to wallplate to allow Construction to Wall plate
- Loft Truss's - Set Out next, ETA to allow Design Completion and Pricing before Top of wallplate Builder to advise target date
- First floor set out - to be final checked once Loft Truss's set out.
20-019 - Lask Edge Chapel Conversion to 4B Residential
Appointment: Stage 1-3, Stage 6 Advisory
- Completion Inspection - BCO pending, works are complete and dwelling advertised for sale
- Completion U Values pending No rush req pre sale
- GA Layouts updated to suit As Buillt - done and issued to SAP assessor
- Ceiling layout to be updated to suite as built lighting - pending
- Liaison with SAP assessor for final as built Spec, Completion SAP and EPC pending
20-049 - Cromer Road EA App
Complete
20-054 - Knowsley Farm: 2S3B Farm full Farm Remodel and Barn Conversion
Appointment: Stage 1-6 Full
- Pre Completion Inspection March 2024 with CPR and Arhcitect, only Drive surface water and kitchen hood ventilation incomplete, Dwelling occupied from Feb 2024.
- Reversion app to DBCP, March 2024 [CPR closed Office]
- Cooker hood installed May 2024, pending drive SW drain install
- Waiting for final CPR cert from administrator, requested by BCO and Architect.
22-014 - Moss House Barns - Executive Barn Conversion One and Two - 2S4B
Appointment: Architect, PD, Stage 1-4, Stage 5 pending
- Second Planning App approved March 2025
- Newt RAMS Statement Planning discharge app pending in workload queue
- Works cannot recommence until RAMs discharged
- Works currently at Superstructure complete except FF Party Wall, Internal Partition Studwork complete, External Windows and Doors complete, Roof Ridge Bat detail to be completed on site, needs set up of ridge tiles, Bird boxes to walls
- F10 will be required prior to works recommencing
22-035 - Blue Grass Purple Cow Nursery: Grade II Listed Nursery Extension and Reconfiguration
Appointment: Stage 1-3 Architect
- Stage 3B Complete application submitted Dec 2024
- Stage 3C Planning and Conservation application in progress, Consultation complete, no adverse comments, response to submitted comments submitted.
Pending Planning Decision, Planners chased twice
- Stage 4 Next, pending planning approval
- Grant Application has been secured subject to expenditure before end of 2025
22-058 - 59th Newchappel Scouts: Two phased Extensions and Internal Alterations
Appointment: Stage 1-3 Architect, Phase 1 - Stage 4-6 - Architect and PD
- Second Planning Application approved 6 Apr 2023 - must be implemented by Apr 2026
- Stage 4 Drawings issued for Tender
- BCO application submitted for plan check
- Stage 4 - SE steel design recieved, to be brought into Architects drawings in workload queue and submitted to BCO
- All BPA Stage 4 dwgs submitted to BCO, Plan check in Progress
- SE Foundation design pending, following Trial pits, witnessed by SE and Architect on site 1 May. Photos sent to BCO.
- Builder ETA to commence foundations August 2025 or sooner
- F10 submission required by end July Builders contact details requested
23-006 - 2 Diamond Way Offices Complete Dec 2023
Appointment: Stage 1-6 Full Architect, PD, Lead Consultant, CA
- 12 Months Defects Inspection 10 Dec 2024
- Second Inspection 13 March 2025
- Certification pending completion of final defects stags, only one item remaining, final works in progress by Contractor
23-044 - Haven - 2SRE and Garage
Appointment Stage 1-3: Architect, PD advisory
- Stage 1A - Survey - 25 April 2025
- Stage 1B - Draw Existing Pending in workload queue
- Stage 2 - Scheme Design pending in workload queue
- Stage 3 -
23-053 - The Workshop Knypersley: Grade II Dwelling LB application
Appointment: Stage 1-3 Architect
- Stage 3 In progress - Listed Building Application registered - 6 June 2024
- Consultation 7 Jan 2025, 17 Jan 2025, Update Chased March, April, Response May
23-060 - Grindley Cottage: 2S4B New Dwelling - Conservation and Proximity to LB application
Appointment: Stage 1-3 Architect, PD Advisory
- Stage 1: Site Appraisal Visit Nov 2023
- Stage 2: Appointment to produce Stage 2 Outline scheme design for Agent valuation complete 11 Oct 2024, 2Storey 4 bed dwelling
- Cleint meeting Nov 2023 agreement to reduce accomodation to 3 bed 2 storey and request for alternative single storey 3 bed
- Advised we require Top surevey, updated tree survey and PEA plus BNG calc
- Quotes for Topo and Tree survey Octo 2023 -
- Topo survey procured mid Nov 2023 delivered 6 Jan
- Discussion with surveyor and supply of dwg of site and original PDF tree survey
- Stage 1 Revit model updated to import Topo survey and start to adjust existing to reflect topo levels, original consultants levels and site info somewhat different to actual site cannot be relied on. Jan 2025
- Client provided additional photos CC requested end Jan 2025
- Further work on existing Stage 1 model April
- Tree survey chased 9 Apr 2025 , delivered
- Tree survey inmported to Revit 9 Apr 2025 -
- BNG and PEA - not appointed yet
- Heritage Consultant - not appointed yet
- Requested additional site photos [ours taken Nov 2023] showing current site and tree condition recived 14 Apr
- Topo survey Levels and Existing site info being adjusted in model to suit, Existing structures walls being reconfigured to suit. original info drawn at previous stage 2 is at original Consultants levels and needs to be dropped to suit topo survey.
- Gave up 11 Apr 2024 and requested a re-exported 3D topo with separate layers from surveyor - now recieved
Work in Progress, drawings not at prev Stage 2 point
- May 2025
- Current level Separate 3D Topo to be re-imported and levels updated as existing
- Current Tree Information - to be updated 50% done
- Once we are at As Existing frozen, amendments and review of original Proposed Stage 2 scheme to be reviewed in relation to levels. and frozen
- Next - 3D outline view to be produced for current Stage 2 design, to respond to planning coments made with Previous planning applicaiton by others
Photos taken from point of observation for 3D outline view recieved from Client
- Next Original proposal to be taken to frozen point, before works commence on alterantive scheme to avoid repetition
- Follow On Client has requested an alternative SS3 Bed option for consideration
24-004 - 24 Dales Gree 2S SE Residential
Appointment: Stage 1-4 Architect, PD Advisory
- Stage 4 Complete and Issued
- Stage 4 Party Wall Notification Complete and Issued
- Works on Site - Boundary Wall complete, Foundations Complete, Superstructure in progress
- CDM with Cleint and Principal Contractor
24-015 - Stoneyfields
Complete
24-032 - Cromer Road Shredder Wall Alterations
Contractors Tender submitted. - Client decision pending 2025-2026 budget
24-037 - Higher Overton Barn: Grade II Barn LB application
Appointment: Stage 1-3 Architect, PD Advisory
- Stage 3 Listed Building Application Repair Works - in Progress
- No adverse comments - Decision pending
- Once approval recived , reconfirm with BCO whether works are applicable , initial email excahnged
24-047 - Shaw Street: 2SRE and Int Alt
Appointment: Stage 1-4 Architect, PD Advisory
- Stage 4 Architect Drawings Complete apart from Steel sizes
- BCO Plan check quote recieved, updated to suit 2S extension plan check required
- SE Calcs and steels required, then incorporate into drawings
24-055 - The Greyhound - Bar and Restaurant
Appointment Phase 1: Stage 1-4 Architect, PD, Some SI, Advisory
Appointment Phase 2: Stage 1-3 Architect, PD, Advisory
Appointment Phase 3: Stage 1-2 Architect
- Phase 1: Refurb Stage 4 drawings Complete
- Phase 1: Internal refurbishment on site, currently at commissioning and cleaning. Works do not involve any internal Change of Use alteration at GF , FF NLB partitions adjsuted to provide 1 additional staff bedroom, no extension
- Phase 1: External Alterations. Stage 3 Planning drawings, updated and resubmitted to Planners as Contractor amended proposals, - pending decision.
Application pending BNG calc for playground area compensation, Ecology visit ETA 10 June
- Phase 1: Signage application submitted for Planning - pending decision
- Phase 2: Marquee siting App, Site Plans produced, Elevations To be produced Workload 2nd Week in June,
- Phase 2: Ecology PEA and BNG ETA Site visit 10 June
- Phase 2: Topo survey 16 May - reived and issued to Tree surveyor
- Phase 2: Tree survey 16 May - production in progress receipt pending invoice
- Phase 2: Elevations of marquee to be produced before mid June
Planning application pending
- Phase 3: FF Alterations - Scheme Design issued, to allow drainage to be accounted at GF exisitng - no further actiion until future date
24-067 - Federation Road Slab Works
Contractors Price issued to Client for agreement
24-074 - HWRC Burslem
Stage 1 EA Plan production Fee submitted
Fee submitted for HWRC Reconfiguartion- waiting for Client PO
24-079 - Land Wheelwrights Lane/Keepers Cottage: 2S4B New Dwelling
Appointment: Stage 1-3 Architect, PD, Lead Consultant
- Stage 1: Site Appraisal Complete
- Stage 1 Topo received, and imported
- Stage 2: Scheme Design complete and agreed with Client
- Stage 3A drawings in progress in workload
- Stage 3B Statutory drawings in progress and advanced in workload
- Stage 3 BNG liasion with Ecologist pending circa 2nd week June 2025
25-008 - 2 The Brake - SSRE, SSSE
Appointment: Stage 1-3 Architect
Stage 1 Survey 19 Feb 2025
Stage 2 Scheme Design March 2025
Stage 3 Planning Application submitted 26 March - approval granted
25-011 - Lower Oxford Road - Conservation Application
Appointment May 2025 : Stage 1-4 Architect, PD
- Stage 1 Survey pending Workload queue
- Stage 2:
- Stage 3:
- Stage 4:
25-013 - Hanford HWRC
EA Plan Update Quote requested
25-014 - Danebank Building Condition Compliance Survey
Quote pending workload
25-018 - Hughson Grove
Quote pending workload advised ETA 2 weeks for quote due to workload
25-019 - Blue grass Purple Cow - Hayfield Nursery - Conservation Application
Stage 3 Advice in progress pending
25-020 - Wayside - SSSE x 2
Quote pending workload requested 21 May 2025 - advised ETA 2 weeks , 2 Months workload queue
25-021 - The Fenns Art Studio
Quote pending workload - resubmission of lapsed Planning Application requested 22 May 2025
25-022 - Ellesmere House
Provide Historic As built dwg's - requested 22 May 2025